This required all fixtures to be removed and the floor surface to be mechanically ground to allow for a new epoxy coating throughout for easier cleaning and impervious hygienic conditions.
This area required full wash out so needed covering to floors & the walls to be sealed properly.
Grinding of floors took a week to complete & it was a requirement that minimal dust to escape from the direct area. This was managed with exhaust fans & industrial Vacuum machines.
The epoxy coatings were a special blend to suit client’s colour & non slip requirements.